Today, we will continue our series of courses about vertical transportation in buildings and this will be our first article in the second course “Course ELEV-2: Vertical Transportation Design and Traffic Calculations”, where we will explain the following points:
Applicable Standards and Codes Used In This Course,
The Need for Lifts,
The Efficient Elevator Design Solution,
Parts of Elevator System Design Process,
Overview Of Elevator Design And Supply Chain Process.
| First: Applicable Standards and Codes Used In This Course |
| Second: The Need for Lifts |
Lifts are installed into buildings for the following reasons:
We can say that lifts must be like toilets, they should be available and easy to use without a long waiting time. Unfortunately this is not always the case and some designs may result in the installation of a non-efficient lift system. Therefore, learning how to design an efficient lift system becomes a necessary especially in high rise and complex buildings and that is what we will explain in this course. |
| Third: Parts of Elevator System Design Process |
| Fourth: The Efficient Elevator Design Solution |
| As a general rule, the target of any engineering design process is finding a compromise between performance and cost of design to get the most efficient and economic design solution. In the elevator design process, the performance and cost are represented by the following parameters:1- Elevator design process’ Performance parameters:
2- Elevator design process’ Cost parameters:
Therefore, the best design should ensure the following requirements:
|
| Fifth: Overview of Elevator Design and Supply Chain Process |
| Step#1: Knowing Building Owner’s Expectations/RequirementsThe Building architects communicate with the Building owner and vice versa to know all the needs, expectations and requirements of the owner from the elevator system. |
Step#2: Gathering the Required Information (Design Parameters)The Building architects and Construction Company Gather all the required information for starting the planning and design phase of the elevator system like A- The owner’s requirements (from step#1), B- The building parameters which are:
|
Step#3: Making Traffic CalculationsThe above data from step#2 to be forward to the elevator design engineers /manufacturer for starting the traffic calculations to determine the following design data:
The above design data must be based on the rules and regulations created by local authorities, public organizations, Building codes, fire regulations, the American Disabilities Act (ADA) and international specific rules like EN81 and ASME/ANSI A17.1 which give detailed documentation of the design criteria which must be met. |
Step#5: Selecting the Suitable Design of the Elevator
|
Step#7: Making Specifications and Commercial Proposal
|
| Step#8: Approval of Commercial ProposalThe building architects and the Construction Company review and approve the commercial proposal submitted by the elevator manufacturer and prepare the contract. |
| Step#9: Approval of Production DrawingsAfter the Construction Company’s approval of the elevator manufacturer’s contract, The elevator manufacturer submits the design and production drawings for approval by the building architects and the Construction Company. |
Step#10: Fabrication, Delivery, Installation, Inspection, Commissioning and Handing Over Of the Elevator System.
Note: Steps#2&3 will be explained in detailed throughout this course. |